A CR662RM has arrived at MVE.
We begin tearing down the machine.

Removed and tagged parts.
Hood is being torn down.

Pumps and motors removed and tagged.

Disassemble the screed.

Steering panels and control boxes are pulled and will be thoroughly rebuilt with new components.

Chains removed, to be replaced.

Hydraulic hoses are being replaced.

Hopper and related parts are removed.

Getting ready to take off the worn wheels.

The old engine is taken out.

Additional parts removed and getting ready for new paint.

All new harnesses and cables are ready to go on the machine.

Freshly painted frame.

Rebuild the control box.

Organized the new control box.

New pumps and hose reel installed.

New tires are installed.
The new hopper is placed.

New main control box assembled.

New hood installed.

Freshly painted parts that are ready to go on the machine.

Chromium carbide liners are in.

New tracks are installed.

New engine assembled and installed.
.jpg/:/cr=t:0%25,l:0%25,w:100%25,h:100%25/rs=w:388,cg:true)
Test driving the paver ensures everything runs smoothly, and then the paver is on its way.